Transmission System
Mozambique
Temane: 400kV, 613 km, 4 new Substations

Duration:
2018 – 2024; STE transmission system was energization in December 2024
Mandate:
Prior to founding EBP, the firm's Managing Partners, Andreas, served as STE Project Director seconded by Globeleq, and Nasir as STE Construction Director
Donors:
World Bank Group, Norfund (Norway), Islamic Development Bank (IsDB), OPEC Fund for International Development (OFID), African Development Bank (AfDB)
Ownership:
STE, a wholly owned subsidiary of EDM
Under the feasibility, development, and construction co-leadership of EBP Managing partners and EDM, and in collaboration with an international multidisciplinary expert team, the Temane Regional Electricity Project (TREP) is anchored by the Temane Transmission Project (TTP), implemented by STE, a wholly owned subsidiary of EDM.
EBP Managing Partners led the project across the full lifecycle, from feasibility and planning through construction to O&M and operations
TTP represents Phase 1 of Mozambique's Tete–Maputo transmission backbone and includes:
- 563 km 400 kV single-circuit line
- 2 x 25 km 400 kV double-circuit line
- Four new 400 kV substations (Pambara, Chibuto, Matalane, Maputo)
The transmission system project evacuates power from the 450 MW CTT IPP while establishing backbone capacity for future large-scale gas, hydro or renewable power generation projects.
Complementary grid reinforcement projects under parallel development and construction include:
- 28 km 110 kV Pambara – Temane extension
- 60 km 275 kV Dzimbene – Chibuto extension